| Case Study
Integrated Process Control & Shutdown
Systems
Abstract
This paper outlines how the separate requirements
of process control and plant shutdown can be met using PLCs in redundant
configuration to achieve high reliability and availability. System
topologies are discussed and an example of an integrated system
recently installed on BP's Forties Alpha oil platform is examined.
Introduction
What is an integrated control and plant shutdown
system? By "integrated", we mean that the process control system
and the shutdown system are supplied by a single company/integrator,
based upon the same PLC equipment range with intercommunication
between the subsystems and a common operator interface. This approach
is being called for increasingly by oil companies around the world.
Prior to the concept of integrated systems,
separate contracts for the process control and shutdown elements,
involving separate suppliers and technologies could potentially
give rise to contractual difficulties and problems with technical
interfaces. Also, separate forms of human machine interface (HMIs)
could be a contributor to the cause of accidents, due to incorrect
interpretation of the state of the plant during process upset conditions.
Another major driver for integrated systems
is the cost saving afforded, due to the need to administer only
one contract for systems supply, as opposed to two or possibly three
associated with earlier approaches. This is in line with the CRINE*
initiative of the oil companies operating in the UK Continental
Shelf, CRINE being a new culture introduced in the 90's to drive
out unnecessary cost. *Superseded by LOGIC
Topology of the Integrated System
Refer to diagram. This illustrates the integration
of separate PLC subsystems for process control, Fire & Gas, shutdown
and mechanical packages, under the umbrella of a common operator
interface, for a typical oil industry project.

PLC System Architectures
A variety of PLC subsystem architectures can
be employed dependent upon the reliability and availability requirements:
Single PLC with single
I/O
Dual channel PLC system
Redundant processors
with single I/O
Redundant processors
with dual I/O
Redundant processors
with triple I/O
Triple redundant PLC
system with triple I/O and 2oo3 voting
Guidelines and Standards
It is necessary to observe the UKOOA guidelines
for instrument-based protective systems and the provisions of international
standard IEC 61508, e.g. in respect of system integrity levels (SIL),
probability of failure on demand (PFD), etc. for all protection
and safety functions.
Integrated Control and Shutdown System for
BP's Forties Alpha Oil Production Platform
This project has been chosen as a case study,
to illustrate the integrated approach.
The flexible characteristics of Rockwell's range
of PLCs allows an integrated solution to be achieved to the problems
of upgrades on the older North Sea oil platforms.
The installation of these upgrades extends the
platform production life by the introduction of:
1. Reduced unplanned
shutdowns.
2. Improved maintainability
through better information gathering.
It will also reduce operational costs due to
the improved production profile and the reduced input from the operations
personnel.
The example chosen is that of the BP's Forties
Alpha Platform where the NGL plant had become the key area of the
operation due to its pivotal role in provision of high pressure
gas for the Deep Gas Lift system installed there in the early 1990's.
Loss of the NGL means loss of the platform's production.
The Pre-Upgrade Situation
The Forties Alpha NGL control scheme, prior
to upgrade, was based on pneumatic controllers and relay based sequencing
and production shutdown scheme.
This scheme, due to its age was unreliable and
was the cause of numerous unplanned shutdowns. By reduction of unplanned
shutdowns the production profile of the plant would be much enhanced
producing benefits of greater production returns and reduced manpower
demands.
Constraints & Objectives
The following constraints were placed on the
design:
1. Shutdown time (oil to oil) was limited to
14 days for completion of installation and commissioning.
2. Physical space was limited
3. Maintenance period to be 5 years
4. Able to be expanded for future upgrades
The Solution
An integrated system was developed based on
two independent PLC subsystems and a common PC - based operator
interface:
1. Process control PLC subsystem
2. Plant shutdown PLC subsystem
Each PLC had a dual processor hot-backup configuration
with BCM & BEM modules for increased fault tolerance. The process
control PLC subsystem was configured for 40 AI, 17 AO and 20 DI.
All 17 PID control algorithms were configured with full alarm generation
for plant parameter deviation monitoring.
The plant shutdown PLC subsystem handled 17
AI, 80 DI and 58 DO. The analogue inputs were configured for trip
functions. This gave increased reliability through the use of out-of-range
monitoring for fault detection, so removing unseen failures possible
with digital inputs, such as pressure switches.
It should be noted that no ESD (Safety Integrity
Level 3) functions are involved, these being performed by a hard
wired relay system.
The logic allowed for complete sequencing of
pump valve arrangements and for the control of the refrigeration
and the glycol gas dryer / recovery plant.
The space constraint was answered by only having
the client PC in the NGL control room plus one server. A further
server was installed in the main central control room.
The PLC's were mounted in an adjacent equipment
room.
The Result
The improved control on the plant has given
the operator more confidence in the performance of the plant. When
shutdowns do occur the information supplied by the SCADA based operator
interface allows for speedy recovery. The unplanned shutdowns are
running well below 10% of pre-upgrade factors. BP have requested
more extensive upgrades to the Forties Delta and enhancements to
the Forties Alpha system, which confirms the success of the scheme.
The upgrade hook up and commissioning was able to be completed in
the shutdown period, the PLC installation and pre-testing having
been completed offshore prior to the shutdown.
The Conclusion
The combination of the flexible PLC based systems
with a PC based operator interface gives a flexible and efficient
solution to the upgrade problem. Production losses which may have
been expected in a major upgrade were avoided by careful use of
time and technology. This makes this approach more attractive and
cost efficient.
|